HSWPE 10
Three generators each of capacity 9000 KW have been installed at a power station. During a certain period of load, the load on the plant varies from 14000 KW to 24000 KW. Determine: (6 mark) Dec 2018
1. Total installed capacity
2. Load factor
3. Plant factor
4. Utilization factor
Answer :
HSWPE 11
A runoff river plant is installed on a river having a minimum flow of 15 cumecs. Head available at the plant is 16 m and the plant efficiency may be assumed as 80%. If the plant is used as a peak load plant operating for 6 hours daily, compute the firm capacity of the plant: (6 mark) May 2018
i. Without pondage
ii. With pondage but allowing 8% of water to be lost in evaporation and other losses